The Task Status View is used to inspect task progress information at a period, set in the configuration.
The tasks are divided into groups dependent on the status of the task:
Not Started |
Tasks that should have been started by now. |
Running |
Tasks that have been started, but not yet finished. |
Finished |
Tasks that were finished in this period |
Next Period |
Tasks that are scheduled to be started in the next period. |
Progress information can be edited in-line as described here or by using the task progress dialog. |
|
The following columns are displayed as default:
Column | Description |
---|---|
Name |
The name of the task. |
Status |
Task status |
% Completion |
Task completion |
Planned Effort |
The amount of work planned to be used at the end of the current period. |
Actual Effort |
The amount of work spent. |
Remaining Effort |
The remaining effort needed to complete the task. |
Planned Cost |
The planned cost at the end of the current period. |
Actual Cost |
The actual cost incurred. |
Actual Start |
The actual start time of the task. |
Actual Finish |
The actual finish time of the task. |