Task Execution View
Progress information can be edited in-line as described here or by using the task progress dialog. |
|
The following columns are displayed as default:
Column | Description |
---|---|
Name |
The name of the task. |
Status |
Task status |
% Completed |
Task completion |
Responsible |
The person responsible for this task. |
Assignment |
The resources assigned to this task. |
SPI |
Schedule Performance Index. (BCWP / BCWS) |
BCWS |
Budgeted Cost of Work Scheduled. |
BCWP |
Budgeted Cost of Work Performed. |
ACWP |
Actual Cost of Work Performed. |
Description |
Task description |