Task Execution View

Description

The Task Execution View is used to inspect task performance information.

Data

Progress information can be edited in-line as described here or by using the task progress dialog.

The following columns are displayed as default:

ColumnDescription

Name

The name of the task.

Status

Task status

% Completed

Task completion

Responsible

The person responsible for this task.

Assignment

The resources assigned to this task.

SPI

Schedule Performance Index. (BCWP / BCWS)

BCWS

Budgeted Cost of Work Scheduled.

BCWP

Budgeted Cost of Work Performed.

ACWP

Actual Cost of Work Performed.

Description

Task description

Configuration

Using the context menu, the view can be configured to show / hide the Project, split / unsplit the tree view or it can be configured using the configure dialog.