Chapter 4. Summary

WIP: Work In Progress. Do not translate!

This view summarizes performance data for the projects in your portfolio.

NameDescription
NameProject name
ScheduleSchedule name
SPI CostSchedule Performance Index (Cost based)
CPI CostSchedule Performance Index (Cost based)
SPI EffortSchedule Performance Index (Effort based)
CPI EffortSchedule Performance Index (effort based)

SPI indicates if the progress is on schedule (1), behind schedule (less than 1) or ahead of schedule (greater than 1). CPI indicates how much it has cost to obtain the actual progress. A value of 1 means as planned, less than 1 means it has cost more than it should have done and a value greater than 1 means that the progress has bean obtained with less resource usage than planned.