Editing data

Progress information can be edited in-line or by using the task progress dialog.

The following columns are displayed as default:

ColumnDescription

Name

The name of the task.

Status

Task status

% Completion

Task completion

Planned Effort

The amount of work planned to be used at the end of the current period.

Actual Effort

The amount of work spent.

Remaining Effort

The remaining effort needed to complete the task.

Planned Cost

The planned cost at the end of the current period.

Actual Cost

The actual cost incurred.

Actual Start

The actual start time of the task.

Actual Finish

The actual finish time of the task.