Progress information can be edited in-line or by using the task progress dialog. |
![]() |
The following columns are displayed as default:
Column | Description |
---|---|
Name |
The name of the task. |
Status |
Task status |
% Completion |
Task completion |
Planned Effort |
The amount of work planned to be used at the end of the current period. |
Actual Effort |
The amount of work spent. |
Remaining Effort |
The remaining effort needed to complete the task. |
Planned Cost |
The planned cost at the end of the current period. |
Actual Cost |
The actual cost incurred. |
Actual Start |
The actual start time of the task. |
Actual Finish |
The actual finish time of the task. |