Resource Assignment View

Description

The Resource Assignment View displays the scheduled task-resource assignments in a table.

Note

This view can severely impact performance in large projects.

Data

The following columns are displayed as default:

ColumnDescription

Name

The name of the object (Resource group, resource, task)

Total

The total assignment for a resource

Dates

The total assignments for a resource per day and the assignments for the resource per task.

Editing data

The task description and progress can be edited using the context menu.