Resource Assignment Gantt View

Description

The Resource Assignment View displays the scheduled task-resource assignments in a table.

Note

This view can severely impact performance in large projects.

Data

The following columns are displayed as default:

ColumnDescription

Name

The name of the object (Resource group, resource, task)

Total

The total assignment for a resource

Dates

The total assignments for a resource per day and the assignments for the resource per task.

Editing data

The task description and progress can be edited using the context menu.

Configuration

Using the context menu, the view can be configured using the configure dialog.

The configure dialog enables you to include or exclude assignments.

Configuration Dialog

Configuration Dialog